Environment · Nigeria
Obtain an Environmental Impact Assessment (EIA) certificate
Get an EIA certificate from the Federal Ministry of Environment for a new project: registration → site verification → EIA study → public display → panel review → approval. Category I projects need a full EIA.
5
3
Who you will deal with
The steps
- Register the project
- Federal Ministry of Environment — Environmental Assessment Dept.
- Pay the registration fee (₦50,000) and collect the project registration/notification form. Projects are classified Category I (full EIA), II (partial ESIA) or III (exempt).
- Project description; proof of registration-fee payment
- Registration stage
- Site verification
- Federal Ministry of Environment
- The Ministry conducts site verification of the proposed location with the proponent and their consultant.
- Site access; project details
- Scheduled
- Conduct the EIA study
- Accredited EIA Consultant (Ministry-witnessed)
- Carry out the EIA study incl. baseline environmental data and laboratory analysis over two seasons, witnessed by the Ministry.
- Baseline data; lab analysis; draft EIA report
- Two seasons
- Public display and panel review
- Federal Ministry of Environment
- The draft EIA report is displayed for 21 working days in affected LGAs and online for public comment, then reviewed by an independent Panel of Experts. Fees scale with category up to ~₦10,000,000 for panel review.
- Draft EIA report (hard + electronic copies)
- 21-day display + panel review
- Approval and certificate
- Federal Ministry of Environment
- On a favourable panel recommendation, the Ministry approves the EIA and issues the certificate (certification fee ~₦100,000).
- Final EIA report; certification fee
- Total ~4-6 months